First step was to find suitable land. Flat not hilly, suitable climate and geographical conditions, dry and not too cold and many other matters to consider, all the way from water and electricity to reasonable access to nearest airport among other things. A suitable place was found in Santa Cruz de la Zarza, an excellent location less than an hour’s drive from the Madrid airport.

Years later today, the end result is a monumental landmark. Not only employing hundreds of people and having a positive impact on the whole region but also helping to test products that are safer in a eco-friendlier way.

Key Milestones 

2013 - Initiative to build a new testing facility

2015 - First designing and planning phase started

2016 - Location and feasibility study
Three locations were considered in Santa Cruz de la Zarza and a geotechnical survey was made to choose the best area.

2018 - Decision to build in Spain
Construction investment decided and approved.  

2019 - Groundbreaking ceremony 

2021 - The opening ceremony and testing started 